CHALLENGE

Los Angeles County, the most populous in the nation, requires large-scale facilities to safely process and manage its substantial waste. Electricity is the Los Angeles County Sanitation District’s (LACSD) largest operating expense, driving its need for affordable, sustainable, and stable energy solutions.


To address this, LACSD issued a request for proposals to build photovoltaic systems for its Palmdale and Lancaster wastewater treatment plants. However, after reviewing submissions, they lacked a clear way to determine which proposal offered the best value and savings.


SOLUTION

Pacifico stepped in to help LACSD assess policies, incentives, and technologies to maximize long-term savings and renewable energy potential. Through a detailed review of the district’s supply contracts, we determined the optimal size for both battery storage and photovoltaic systems. 


By submitting timely interconnection requests, Pacifico secured full net metering treatment for these facilities. Additionally, the team obtained incentive funding for the battery storage system through the California Self-Generation Incentive Program (SGIP) to offset battery costs.

RESULTS

Currently under construction, these projects will enable LACSD to lock in electricity rates below those of CA utilities and third-party suppliers, maintaining stable costs over a 25-year energy services agreement (ESA). 


Additionally, the batteries will offset peak site usage to reduce demand costs in addition to providing a sustainable source of backup power.


The facilities will operate on 100% renewable energy while seamlessly integrating with existing diesel generation backup power systems, ensuring uninterrupted operation during grid disruptions.

DETAILS

Solar Power Generation

11 MW

Battery Storage Capacity

4 MWh

Offtaker of Electricity

Los Angeles County

Location

Lancaster & Palmdale, California

Commencement of Construction

Early 2025

Date of Commercial Operation

Fall 2025 (Expected)

Status

In Construction

Other Case Studies

Explore more of our energy case studies from around the world, each one tailored to meet unique challenges and deliver measurable impact.

Electric Utility / Wholesale

30 MWdc

Food Manufacturing

5.5 MWdc

Community Solar

6.5 MWdc

Electric Utility / Wholesale

54.8 MWdc

Water & Wastewater Utility

11 MWdc

Data Center

432 MW

Let's Talk

What are your organization’s energy-saving objectives?

My Organization wants to...
panels-trees.jpg
Half-image-before.jpg
bottom of page